Completed
Mine Action projects
Project Start Date
08 Dec, 2021
Project End Date
15 Jun, 2022
Location
Kadugli
Sector
Mine Action
Year
2021 - 2022
five and half-month project (8 Dec 2021 to 15 June 2022), funded by UNOPS through UNMAS. The project capacity included; four multi-tasking teams and one manual clearance team. During the grant period, the land release operations covered four areas; Umhetan village, Abu-Karshola locality, Alhamra village, and Daloka village in South Kordofan. The project. Teams released 53,850 square meters of land for productive use. As a result of the land release operations, 3,481 items of explosive ordnance were destroyed. In addition to clearance activities, the teams conducted explosive ordnance education sessions reaching 2786 individuals living in the contaminated areas.